SAFe – Scaled Agile Question Bank 6

 

51. Which statement is true about fast feedback?
It accelerates planning and delivery
Smaller batch sizes enable faster feedback loops
It supports SAFe Lean-Agile Principle #3 – Assume variability; preserve options
The shorter the feedback cycle, the higher the utilization

52. The goal is a fast delivery process, ideally requiring little manual effort. What is one capability used to achieve this?
Soft launches
Non-functional requirements
Feature toggles
Quiet releases
What should a team do if they cannot meet their commitments?
Deliver what the team can complete with open issues
Escalate immediately to Product Manager through the Product Owner
Move what cannot be accomplished into stretch objectives
Review the objectives and reset them to fit what can be done
53. What should a team do if they cannot meet their commitments?
Deliver what the team can complete with open issues
Escalate immediately to Product Manager through the Product Owner
Move what cannot be accomplished into stretch objectives
Review the objectives and reset them to fit what can be done

54. What is the purpose of an Epic Hypothesis Statement?
It provides enough detail to run the business and keep long-term commitments from interfering with changing business priorities
It defines an idea that can be validated using the plan, do, check, and adjust cycle
It is the artifact Epics use to get approval to go on the Portfolio Backlog from the Lean Portfolio Management
It helps define the pipeline with the assets and technologies needed to deliver solution value

55. Product Management is involved in the assessment of metrics including the evaluation of business value achieved versus plan. They are also active participants in what else?
Daily Stand-ups
Lean budget establishment
Team Retrospectives
The Inspect and Adapt event

56. What is one benefit of constant customer feedback?
It reduces the amount of changes to the Features
Fast learning cycles
It reduces the need for face-to-face collaboration
Teams can better align working days with a customer’s schedule

57. The Lean Governance collaboration include the Enterprise Architect, Agile PMO, and which other function?
Solution Management
Business Owners
Product Managers
Epic Owners

58. What is the importance of the Definition of Done?
It prioritizes the work of testers on the team
It creates standardized work between all Agile teams
It provides a way for Scrum Masters to enforce quality
It creates a clear understanding of when items are complete
59. SAFe recommends separating deployment from release. What can help with this practice?
Deploying to staging every 4 to 8 weeks
Manually test Features and non-functional requirements
Hide all new functionality under feature toggles
A staging environment that emulates testing

60. What are two examples of team level events? (Choose two.)
System Demo
Backlog Refinement
PI Planning
Daily Stand-up
Scrum of Scrums

61. Which attribute describes the Product Manager role in the SAFe enterprise?
Provide governance and spending practices for value streams
Plans the activities for the Inspect and Adapt event
Collaborates and sets expectations with Product Owners, stakeholders, customers, architects
Uses Iteration Goals to communicate with management

62. What is the goal of Lean thinking?
Best quality and value for people and society
Leadership support
Relentless improvement
Respect for people and culture
63. Which two concepts drive the mindset for SAFe implementation? (Choose two.)
Enterprise Agility
Scrum Manifesto
Agile Manifesto
House of Lean
Lean Enterprise Systems
64. Which cycle is embraced by the Lean startup movement?
Explore-Integrate-Deploy-Release
Plan-Execute-Review-Retro
Hypothesize-Build-Measure-Learn
Plan-Do-Check-Review

65. What is the relationship between a Product Owner (PO) and a Product Manager (PM)?
The PO contributes to the Program Backlog; the PM establishes Story acceptance criteria
The PO drives PI Objectives; the PM drives Iteration Goals
The PO identifies market needs; the PM is solution, technology, and team facing
The PO is team-oriented; the PM is market-orie nted

One Reply to “SAFe – Scaled Agile Question Bank 6”